Order No. 2002-AGR-528

December 16, 2002

December 16, 2002

IN THE MATTER OF an agreement between the Canadian National Railway Company and the Municipality of Whitestone pursuant to subsection 101(2) of the Canada Transportation Act, S.C., 1996, c. 10, relating to the installation and maintenance of the crossing warning system at Bunny Trail North and mileage 170.12 Bala Subdivision, in the municipality of Whitestone, in the province of Ontario.

File No. R8050/326-170.12


On August 1, 2002, the Canadian Transportation Agency (hereinafter the Agency) received a letter from the Canadian National Railway Company dated July 25, 2002, which enclosed a copy of an executed Agreement entered into by itself and the Municipality of Whitestone, with respect to the work set out in the title.

Pursuant to subsection 101(2) of the Canada Transportation Act (hereinafter the CTA), the above-noted Agreement becomes an order of the Agency authorizing the parties to construct or maintain the crossing, or apportioning the costs, as provided for in the Agreement.

Accordingly, pursuant to subsection 101(2) of the CTA, the above-noted Agreement is an Order of the Agency as of August 1, 2002.

Date modified: