Consultation on the Application for Authorization of the Lac-Mégantic Rail Bypass Project
The Canadian Transportation Agency (Agency) invites the public to submit comments on the application filed on September 19, 2025, by the Canadian Pacific Railway Company (CPKC). This application is to construct a 12.5 km long railway line with the aim of moving railway operations outside downtown Lac-Mégantic (Lac-Mégantic rail bypass).
Important Notice
Extension of the written consultation period until January 30, 2026, and of the in-person consultation sessions on December 2, 2025, from 1 p.m. to 5 p.m. and from 6 p.m. to 9 p.m.
1. Background
The Canada Transportation Act requires Agency approval for the construction of all federally-regulated railway lines. For this purpose, two Agency members have been designated to determine whether the requested construction must be authorized, authorized with conditions or dismissed.
Agency members are appointed by the Governor in Council and issue decisions based on arguments and evidence found in the application record and any other information that they may request. It should be noted that members act independently, that is to say that they do not represent either the government or the railway company and that no party is authorized to influence their decision. When they assess a construction application, their role is to render a decision based on the proposed route and not to determine the optimal route. Therefore, in the case of the Lac-Mégantic rail bypass, members will rule on CPKC’s proposed route.
In order to assess applications for the construction of a railway line, the Agency will follow the four steps of the process as shown below. We are now at step 2.
- Confirmation that the application is complete for consultation purposes
- Consultation period
- Member deliberations
- Final member decision (determination)
The Agency will authorize the construction of a railway line if it determines that the location of the line is reasonable based on the following factors:
- requirements for railway services and operations; and
- interests of the localities affected by the railway line.
For more information on the Agency’s process, please refer to How to Apply for Approval to Construct a Railway Line: A Guide for Federally Regulated Railway Companies.
2. Project information
On July 6, 2013, a freight train made up of 72 tank cars carrying crude oil was parked at the top of a hill in Nantes, Quebec, and derailed in Lac-Mégantic, Quebec. The ensuing tragedy left 47 people dead.
On May 11, 2018, the Prime Minister of Canada and the Premier of Quebec announced project funding for a 12.5 km rail bypass in order to avoid going through Lac-Mégantic’s downtown core.
At Transport Canada’s request, CPKC filed with the Agency an application to construct a railway line, pursuant to section 98 of the Canada Transportation Act.
CPKC proposes constructing a new railway line with a route that would cross the municipalities of Frontenac, Lac-Mégantic and Nantes between mileage 113.27 in the Moosehead Subdivision and mileage 3.49 in the Sherbrooke Subdivision.
3. Map
Text description of the map
The image shows the map of the proposed Lac-Mégantic rail bypass route, which would pass through the municipalities of Nantes, Lac-Mégantic and Frontenac.
- Selected route: the proposed bypass (shown in blue on the map).
- Existing track: the current alignment that would be dismantled if the proposed bypass comes into service (shown in red on the map).
- Industrial park area: the marshalling and storage area in Lac-Mégantic (shown in green on the map).
The map presents the general alignment between the three municipalities, showing the industrial sector and distinguishing the proposed route from the actual railway right-of-way.
4. Call for In-Person or Written Comments
The Agency finds that the application for authorization of the Lac-Mégantic rail bypass project filed by CPKC is complete for the consultation’s purposes.
The public is now invited to submit comments either in writing or in-person on the following questions:
- How would the location or operation of the proposed railway line affect you? Describe any expected benefits or concerns you have with the proposed line.
- If you have concerns about the proposed railway bypass, what could be done to address them
4a. How to submit written comments
You have until 11:59 p.m. Eastern Standard Time on January 30, 2026, to submit your written comments to megantic@otc-cta.gc.ca.
All information received by the Agency on the subject of this consultation will be filed in the application’s public archives. Comments, including the author’s name, may be published on the Agency’s website.
4b. In-person public consultation session
For interested persons and organizations, the Agency will hold in-person consultations at Lac-Mégantic on December 2, 2025, at the Complexe Sportif Mégantic, Bestar room (5400 Papineau, Lac-Mégantic). Two meeting times will be offered: the first from 1:00 p.m. to 5:00 p.m. and the second from 6:00 p.m. to 9:00 p.m. It will not be possible to participate virtually.
Persons or organizations who would like to participate at one of the two in-person consultation sessions must register ahead of time by sending their full name and which session(s) they wish to attend to megantic@otc-cta.gc.ca. Please note that the registration period for speaking is now closed.
5. Media
Media interested in attending the consultation session being held at Lac-Mégantic on December 2, 2025, must register ahead of time by sending an email at media@otc-cta.gc.ca.
By registering, media are expected to respect the following rules:
- Photographing and recording is permitted only in a designated area until the end of the session’s opening remarks.
- Media are not authorized to speak or ask questions during the consultation session.
- Interviews with interested parties must take place outside the room where the consultation session will take place.
6. Reference documents
All reference material is found on Transport Canada website.
7. Submissions
Disclaimers
Third-party information liability disclaimer
Some of the information on this web page has been provided by external sources. The Canadian Transportation Agency (Agency) is not responsible for the accuracy, reliability or currency of the information supplied by external sources. Content provided by external sources is not subject to official languages, or privacy and accessibility requirements. All submissions are made available in the official language in which they were received.
Privacy notice
Participants were advised that all submissions would be considered a public document and may be posted on the Agency’s website. Participants were advised not to include any personal or confidential information.
| Name of person or organization | Submission date | Submission |
|---|---|---|
| François Demers | November 12, 2025 | Submission from François Demers PDF (82 KB) – French |
| Claire Lemay | November 12, 2025 | Submission from Claire Lemay PDF (77 KB) – French |
| Josiane Gosselin | November 14, 2025 | Submission from Josiane Gosselin PDF (86 KB) – French |
| Lina Bolduc | November 14, 2025 | Submission from Lina Bolduc PDF (83 KB) – French |
| Remi Tremblay | November 14, 2025 | Submission from Remi Tremblay PDF (95 KB) – French |
| Gabriel Grenier | November 15, 2025 | Submission from Gabriel Grenier PDF (78 KB) – French |
| François Charbonneau | November 17, 2025 | Submission from François Charbonneau PDF (91 KB) – French |
| Francis Paré | November 19, 2025 | Submission from Francis Paré (#1) PDF (203 KB) – French |
| Nancy Roy | November 19, 2025 | Submission from Nancy Roy PDF (85 KB) – French |
| Vincent Spica | November 19, 2025 | Submission from Vincent Spica PDF (79 KB) – French |
| Pierre-Luc Bureau | November 20, 2025 | Submission from Pierre-Luc Bureau PDF (104 KB) – French |
| Municipalité Frontenac | November 20, 2025 | Submission from Municipalité Frontenac PDF (363 KB) – French |
| Réal Grondin | November 20, 2025 | Submission from Réal Grondin PDF (77 KB) – French |
| Georgette Lavoie Louise | November 20, 2025 | Submission from Georgette Lavoie Louise PDF (80 KB) – French |
| Catherine Sophie Bilodeau | November 20, 2025 | Submission from Catherine Sophie Bilodeau PDF (165 KB) – French |
| Rémi Kirouac | November 20, 2025 | Submission from Rémi Kirouac PDF (133 KB) – French |
| Anne Gauvin | November 20, 2025 | Submission from Anne Gauvin PDF (80 KB) – French |
| Maryse Hallé | November 20, 2025 | Submission from Maryse Hallé PDF (80 KB) – French |
| Germaine Roy | November 22, 2025 | Submission from Germaine Roy PDF (86 KB) – French |
| Serge Liard | November 22, 2025 | Submission from Serge Liard PDF (86 KB) – French |
| Lise Blais | November 23, 2025 | Submission from Lise Blais PDF (89 KB) – French |
| Robert Bellefleur | November 23, 2025 | Submission from Robert Bellefleur (#2) PDF (3 590 KB) – French |
| Claude Roy | November 24, 2025 | Submission from Claude Roy PDF (91 KB) – French |
| Gaston Quirion | November 24, 2025 | Submission from Gaston Quirion PDF (84 KB) – French |
| Robert Bellefleur | November 24, 2025 | Submission from Robert Bellefleur (#1) PDF (88 KB) – French |
| Francis Paré | November 24, 2025 | Submission from Francis Paré (#2) PDF (133 KB) – French |
| Maurice Gareau | November 24, 2025 | Submission from Maurice Gareau PDF (84 KB) – French |
| Claude Roy | November 25, 2025 | Submission from Claude Roy PDF (77 KB) – French |
| Louyse Louis-Seize | November 25, 2025 | Submission from Louyse Louis-Seize PDF (80 KB) – French |
| Anne-Julie Hallée | November 25, 2025 | Submission from Anne-Julie Hallée PDF (123 KB) – French |
| Louisette Rancourt | November 26, 2025 | Submission from Louisette Rancourt PDF (88 KB) – French |
| Anne Dupuis | November 26, 2025 | Submission from Anne Dupuis PDF (80 KB) – French |
| Francis Paré | November 26, 2025 | Submission from Francis Paré (#3) PDF (197 KB) – French |
| François Charbonneau | November 26, 2025 | Submission from François Charbonneau (#2) PDF (114 KB) – French |
| Julie Boucher | November 29, 2025 | Submission from Julie Boucher PDF (178 KB) – French |
| Benoît Morin | December 1, 2025 | Submission from Benoît Morin PDF (84 KB) – French |
| Doris Dion | December 2, 2025 | Submission from Doris Dion PDF (88 KB) – French |
| René Pepin | December 2, 2025 | Submission from René Pepin PDF (84 KB) – French |
| Caroline Rancourt | December 2, 2025 | Submission from Caroline Rancourt PDF (88 KB) – French |
| Danielle Sabourin | December 2, 2025 | Submission from Danielle Sabourin PDF (88 KB) – French |
| Isabelle Samson | December 2, 2025 | Submission from Isabelle Samson PDF (143 KB) – French |
| Suzanne Bizier | December 4, 2025 | Submission from Suzanne Bizier PDF (84 KB) – French |
| Richard Fortin | December 4, 2025 | Submission from Richard Fortin PDF (84 KB) – French |
| Linda Lacasse | December 4, 2025 | Submission from Linda Lacasse PDF (84 KB) – French |
| Rock Lacroix | December 4, 2025 | Submission from Rock Lacroix PDF (84 KB) – French |
| Municipalité Nantes | December 4, 2025 | Submission from Municipalité Nantes PDF (84 KB) – French |
| Francis Paré | December 4, 2025 | Submission from Francis Paré (#4) PDF (84 KB) – French |
| Michel Tanguay | December 4, 2025 | Submission from Michel Tanguay PDF (84 KB) – French |
| Françoise Périnet | December 4, 2025 | Submission from Françoise Périnet PDF (84 KB) – French |
8. Responses
| Name of person or organization | Response date | Response |
|---|---|---|
|
November 14, 2025 | CPKC response – Batch 1 PDF (160 KB) |
|
November 19, 2025 | CPKC response – Batch 2 PDF (1.05 MB) |
|
November 21, 2025 | CPKC response – Batch 3 PDF (130 KB) |
|
November 27, 2025 | CPKC response – Batch 4 PDF (111 KB) |
|
November 27, 2025 | CPKC response – Batch 4A PDF (150 KB) |
|
December 2, 2025 | CPKC response – Batch 5 PDF (142 KB) |
9. Milestones
Milestones
| Date | Status |
|---|---|
Wednesday, November 12, 2025 | Start of the consultation and submission of written comments |
Wednesday, November 26, 2025 | Deadline to register for the in-person consultation in Lac-Mégantic |
Tuesday, December 2, 2025 | In-person consultation in Lac-Mégantic |
Friday, January 30, 2026 | End of the consultation and submission of written comments |